A Brief Analysis of the Masonry Methods and Key Points for the Large Vault of Float Glass Furnaces


Release time:

2024-03-11

As the foremost of the three major thermal equipment units in glass production, the melting furnace is a critical piece of equipment for float glass manufacturing. Among these components, the vault of the melting furnace—the “heart” of the entire furnace—is particularly distinctive. It features a large span, an overall length that demands careful engineering, and a substantial quantity of refractory materials. During operation, it endures the effects of high-temperature gas flows, leading to unpredictable thermal expansion. The quality of its construction directly impacts the furnace’s service life, the degree of thoroughness with which raw materials are melted, and the yield and quality rate of finished float glass products. This article summarizes our company’s construction methods and experiences gained from having undertaken the construction of more than 20 float glass production lines.

7 (1) Process Principle

The installation quality of the large vault wooden formwork and the large vault masonry is strictly controlled by using precision and reliable testing instruments as well as scientifically sound construction techniques. Various control lines are established to ensure the quality of each ring of vault bricks, thereby guaranteeing the installation quality of the large vault in the float glass melting furnace.

21

(2) Construction Process Flow and Key Operation Points

1. Process flow for the fabrication and installation of wooden molds

 Procure materials

2. For wooden molds, red pine is generally used as the material. It should be properly dried and stored in a place protected from rain and moisture according to design specifications. Wood with knots or cracks must not be used in the fabrication of wooden molds.

3. Before fabrication, the arch radius and central angle should be calculated and determined based on the parameters—such as arch span and rise—provided in the design drawings. Then, using the calculated arch radius and central angle, layout work should be carried out on the platform, followed by material cutting and fabrication.

4. Points to note: After the large arch formwork sections have been fabricated, they should be assembled on a platform for inspection. The center of the wooden arch formwork must be checked, and the deviation should not exceed 3 mm. Additionally, use an arc template to verify the curvature of the wooden arch formwork. Arrange the fabricated formwork pieces in sequential order for easy installation. At the same time, avoid exposing them to direct sunlight or rain to prevent deformation.

16

5. Installation of wooden forms

① After the brickwork of the pool bottom, pool walls, breast wall, and side arches is completed, proceed with the installation of wooden formwork. When installing the wooden formwork, first locate the longitudinal centerline of the melting furnace, and once this line is determined, begin installing the upright posts.

② After all the upright posts have been installed, secure them longitudinally and laterally using strips of wood in a diagonal bracing configuration. Then proceed with the installation of the arch ribs, ensuring that the spacing between the arch ribs is maintained within the range of 480 mm to 500 mm. Use strips of wood to connect and secure the arch ribs. Once all components are in place, lay down a layer of plywood. Leave an expansion joint of 30 mm between adjacent plywood sheets.

17

③ Project the longitudinal centerline onto the arch crown and make adjustments to the center, height, and curvature. The deviation between the longitudinal center of the wooden formwork and the longitudinal centerline of the melting furnace shall not exceed 3 mm, and the height deviation shall be controlled within the range of 0 to +5 mm.

④ After the wooden formwork is installed to meet masonry requirements, use wooden wedges on both sides to brace against the breastwall, and ensure that the vertical posts are not left unsupported.

⑤ Precautions during wooden formwork installation: The two ends of the arch slab must be cut into straight edges, with a minimum distance of 50 mm from the arch corner bricks. When laying plywood, expansion joints must be left to prevent arching when the vault is tightened; these expansion joints should, as far as possible, be avoided in areas marked by chalk lines. At the expansion joint between every two sections of the vault, install supporting joists that follow the curvature of the arch. The height of these joists should be roughly 20–30 mm higher than the arch’s apex, so that control lines can be securely attached.

4

(6) Construction of large arch bricks

① Pre-schedule

After all the wooden formwork installation work is completed, proceed with the preliminary arrangement of the arch bricks. At each end of every arch segment, arrange one ring of bricks in advance. The actual dimensions obtained from the on-site preliminary arrangement will be used to determine the size of the mortar joints; however, the maximum width of the mortar joints should be kept within 1.5 mm. At both ends of the arch and at expansion joints, install one pre-fabricated, highly curved support frame. This frame should extend 20–30 mm above the surface of the arch bricks, facilitating the alignment of strings.

14

② Line laying

To ensure the overall aesthetic appeal of the large arch and to avoid any step-like misalignments, a control line should be laid out every 2–3 rings according to the thickness of the arch bricks. Using the centerline of Furnace No. 1 as the reference, mark out the control lines for each expansion joint and the positions of the thermocouple holes. Similarly, mark control points along the keel beams at both ends of each section; these points will serve as the reference for stretching the guideline across the surface of each ring of arch bricks. After completing the layout work, place one-fifth of the total bricks required for the large arch onto the wooden formwork and observe the load-bearing performance of the formwork. If no abnormal conditions such as sinking or deformation of the formwork are detected, you may proceed with the masonry of the main arch.

6

③ Masonry

The arch masonry should be completed within a relatively short period, ensuring that the locking bricks are set before the mortar dries. For large arches, it is advisable to avoid having too many workers present; one skilled mason should be assigned every two meters along the length of the arch. During formal masonry work, construction should proceed simultaneously from both sides toward the center at a consistent pace. If brick cutting is necessary, the cut bricks should be placed in the middle section, with the upper and lower courses staggered. The cut bricks must not be smaller than 130 mm in size.

2

During masonry work, the large and small ends of arch bricks must never be placed upside down. Each brick must be laid using mortar, and the mortar filling in both the horizontal joints and head joints must reach a fullness of at least 95%. Use a rubber mallet or a wooden mallet for alignment. After completing each ring, use a template to check the angle of the vault bricks, and employ a 4-meter aluminum ruler to verify the flatness.

3

After laying 20 rings on each side, perform a preliminary alignment. If no changes are observed, proceed with construction as planned. When you reach the middle and have 15 rings remaining, perform another preliminary alignment. If any changes are detected, make the necessary adjustments. Finally, lay the last three rings in an alternating, interlocking pattern, leaving one ring unoccupied for the locking brick. The locking brick should be positioned one ring toward the center, which will facilitate the installation of the temperature-measuring holes. The protruding portion of the locking brick should ideally measure between 80 mm and 100 mm. After completing each section, uniformly drive in the locking bricks. When driving in the locking bricks, place a wooden board beneath the arch bricks to prevent the large wooden mallet from directly contacting the arch bricks. Once the entire arch is locked, thoroughly clean the arch crown and then fill the joints with a diluted mortar.

8

④ Tighten the strip

After the large arch is completed, the tension bars should be immediately tightened. Before tightening the tension bars, remove the temporary fixings from the steel components and the wooden wedges from the side parapets.

The tensioning straps are used to integrate the brickwork of the entire vault with the supporting steel structure into a single, unified whole. The exact number of straps required depends on the span of the arch, typically being around 1‰ of the arch span. Generally, the magnitude of the force acting on the vault crown is reflected by observing how much the vault crown rises upward under the horizontal tensile force exerted by the straps—this is done through direct observation of changes in the vault crown’s position. The upper part of the vault is suspended with wires, each fitted with a coordinate marker positioned near the straps at the head, middle, and tail of the vault.

10

When tightening the tie rods, proceed one by one from the large arch crown to the large arch tail. At both ends of each tie rod, assign operators to simultaneously and gently tighten the nuts with equal force. However, do not tighten them all at once; instead, repeat the process back and forth, taking an interval of about 0.5 to 1 hour between each cycle, until the large arch is tightened and begins to bulge upward. After reaching the designed reading, maintain the tension for 8 hours and observe carefully. Only when the readings no longer change can the formwork be removed.

⑤ Remove wooden formwork

Remove the wooden wedges beneath the supporting columns, allowing the entire wooden formwork to drop by about 100 meters. Perform a rough inspection of the overall condition of the large arch. Then, use wooden strips to lift the formwork upward, separating the plywood and battens from the wooden arch core. Start by removing the three outermost pieces of the wooden arch core from the tail end, and subsequently lay down the remaining pieces one by one from back to front. Inspect the lower curved surface of the large arch for any chipped or broken arch bricks or other irregularities that should not be present; if any are found, replace them promptly. Finally, proceed with grouting and cleaning. 2422252627

The steps outlined above represent our company’s methods and insights for constructing the vault of float glass furnaces.

Our company has successfully applied the aforementioned construction method in the masonry of large arches for dozens of float glass production lines, including the Hubei Yijun Project, Shandong Yixin Optoelectronics, and Weihai Zhongbo. This approach—characterized by short construction periods, high-quality workmanship, and low costs—has earned unanimous praise from both the design and construction units. It has enabled us to gain a strong foothold in the market externally and generate significant economic benefits internally. Currently, our company is undertaking construction on three float glass furnace projects. The construction of float glass furnaces has become one of our company’s core businesses, accounting for approximately 30% of our total business volume.